No, that's not currently possible. The reason is that Asana only recently began supporting the entry of a time-of-day value for its Start Date. We have not yet had a chance to add support for this feature to Flowsana.
Dynamic Duration Workflows
Last updated on 31 Oct, 2025
No, that's not currently possible. The reason is that Asana only recently began supporting the entry of a time-of-day value for its Start Date. We have not yet had a chance to add support for this feature to Flowsana.
Related Articles
How Dynamic Duration Workflows Work
The Dynamic Duration Workflow lets you build templates based on task durations. Then when you start a new project based on that template, simply fill in the project's start date (or due date for a Workback workflow) and Flowsana automatically sets the correct dates for all of the project's tasks. Whenever you need to make an adjustment to a task, just modify its duration and Flowsana automatically adjusts all of its dependent tasks.
How to Set Up a Dynamic Duration Workflow