When I specified a Duration of two weeks ("2w"), Flowsana created a task length of 20 days, not 14 days

Dynamic Duration Workflows

When I specified a Duration of two weeks ("2w"), Flowsana created a task length of 20 days, not 14 days

Updated 1 week ago

That's probably because you selected the Skip weekends option when you created your workflow template. In that case Flowsana calculates in terms of working days, and it skips and ignores weekends.  So it interprets "2 weeks" as 14 working days.